Major Milestones:

Major strategic plan components identified by mid-June

Planning Committee kick-off by end of June

Public Input Meeting by end of July

Issue Request for Proposals (RFP) to property owners and proposed operating entities by end of August

Receive responses to RFP by mid-September

Prepare Memorandum of Understanding (MOU) with operating entities for proposed site location by mid-October

Facility Design preliminary recommendation prepared by end of October

Operating MOU recommendation prepared by end of October

Funding recommendation prepared by mid-November

Presentation to joint meeting of City Council, School Board, Simpson